Florida Atlantic University Excerpt from: Development Strategy in the South Dade U.S. 1 Corridor Speeding up the Permitting Process At the request of the Florida Department of
Community Affairs the Joint Center for Environmental and Urban Problems at Florida
Atlantic University in August of 1996 published a study entitled: Planning Tools,
Preparing to Implement the Comprehensive Corridor Development Strategy in the South
Dade U.S. 1 Corridor. Though the study focused on south Dade, there
was some excellent discussion on the problems associated with Dade County's building
permit process. Here are some excerpts: Chapter 7. Streamlining the Development
Process in South Dade 7.1. Background Task 9 of the South Dade Project Phase II,
"Prepare Amendments to LDRs Needed to Streamline Development Approval Process,"
focused on amending land development regulations (LDRs) as a means to promote the
streamlining of the development approval process. The corridor/urban center ordinances
are the vehicle the Joint Center and the South Dade Planning and Design Work Group
have proposed to promote development within the study area. The ordinances will
amend Dade County's LDRs for development within the corridor and will thereby provide
a degree of streamlining of the development approval process. The ordinances will
include explicit design guidelines. If followed, these guidelines will provide the
developer with certainty and make the development permitting process go more quickly
If the developer wishes to deviate from these guidelines, then the permitting process
will take longer. The ordinances will give the developer a good idea of what is
acceptable and expected within the corridor. Basically, if there is a predictable process
for certain types of development, it will increase the developers' certainty, reduce
delays, and decrease the financial risks. Therefore, the two corridor zoning ordinances
will be the primary way that the South Dade U.S.1 corridor project will streamline
the development approval process within the corridor for the types of development
the Work Group wants to promote. The design features desired in the study area will
emphasize higher density, mixed-use development in a pedestrian/mass transit friendly
environment. This section of the report will look primarily
at streamlining the development approval process itself, especially its administrative
procedures. The Metro-Dade County Manager's Task Force on Construction Regulations
has already issued a final report on this issue. Its focus is more on interdepartmental
coordination than on the plan processing aspects that are of more concern to this
corridor study Therefore, the Joint Center's task overlaps with the County Manager's
effort, but does not duplicate it. The Joint Center's focus is not on streamlining
the county's development permitting process in general, but on how the development
permitting process could be improved within the U.S. 1 corridor as an incentive
to attract developers to the area. 7.2. Difficulties of Streamlining the Development
Permitting Process The main question that arises when discussing
streamlining the development approval process is how to reduce the planning staff's
discretion while maintaining flexibility for creative development projects. On the
one hand, ordinances promoting streamlining have to be designed to reduce discretion,
because discretion can produce delays and uncertainty of approval. On the other
hand, reducing discretion could lead to reduced flexibility and less creative designs
by developers. In general, developers want two things: 1. Certainty. They want to know what to expect.
They want to know for sure that, if they follow certain guidelines, they will get
approval. 2. Efficiency. They want the process to move
quickly. Delays increase developers' carrying costs and financial risks (DeGrove
1996). According to Reinaldo Villar, assistant director
for the Zoning and Permitting Division, Metro-Dade County, the main complaints heard
from developers about the county's development permitting process is that there
is too much nitpicking of small things, too much detail required, and it simply
takes too long to get a permit. The Corridor Zoning Ordinances are taking an
approach that will increase certainty for the developer by decreasing the amount
of discretion left to the reviewers. As part of the review criteria, checklists
will be included in the ordinances. The checklists will contain features of developments
requiring review for consistency with the ordinances and with planning policies
contained in the CDMP The checklists will provide guidance for planning and permit
reviewers. They will also add consistency to the review process because all reviewers
will follow the same checklist for projects within the corridor. 7.3. Metro-Dade County Permitting Process It is beyond the scope of this chapter to comment
on or recommend changes to the organizational structure of the Metro-Dade Planning,
Development and Regulation Department. The permitting process within a large, metropolitan
county is necessarily complex. There are several types of processes and each process
involves several steps. These processes were laid out in the 1989 Guide to the Building
Permit Process for the unincorporated Areas of Metro-Dade County, a booklet developed
and distributed by the Greater Miami Chamber of Commerce. It represents the latest
handbook available to the public, but is considered outdated by the department.
The procedural steps of the process itself have not changed greatly; however, the
handbook does not explain the issues of concurrency or impact fees, or the new streamlining
changes. A new handbook is being prepared. A communications expert has been hired
to design brochures and pamphlets to explain the process to the public. At this
time, there is a manual for owner-builders, but not for commercial or residential
developers (Villar 1996). 7.3.1. The Development Permitting Process A building permit is needed whenever repairs
or renovations to any structure exceed $500. Plans for repairs or renovations totaling
over $5,000 require a seal from an engineer or architect. The permitting process
has been basically the same since at least 1973, except for the years immediately
following Hurricane Andrew Permitting is divided into two processes: walk-throughs
and drop-offs. Walk-throughs are taken weekdays between 8:00 and 11:00 a.m. Small,
individual projects - such as additions to single-family houses of less than 1,000
square feet, pools, fences, satellite dishes, and interior renovations of commercial
buildings - go through this process. Approximately 150 applicants are serviced through
the walk-through process each morning before noon. The permitting division is divided
into "pods," each of which looks at the various aspects of the project
design. The pods include building and roofing, plumbing, electrical, and mechanical. Every other type of permitting is handled through
the drop-off process in the afternoons. All parts of the application review are
handled on the same floor. These applications are routed by the department and handled
in the order received. Less experienced processors handle residential projects.
More experienced processors handle commercial projects. This is how the process operates now, and basically
how it operated until Hurricane Andrew Following Andrew the staff was divided with
some processors handling only walk-throughs and others handling only drop-offs.
This caused some animosity among staff, because walk-through permits are more confrontational
-- and therefore more difficult -- than drop-offs. Because of the increased number
of permit requests, and because the building code was continually being adjusted,
permitting time increased during the post-Andrew period. In January 1996, the original system was put
back in place with some adjustments. Everyone was once more expected to handle both
walk-throughs and drop-offs. At first, walk-throughs had been lasting until 4 p.m.
More clerks were hired to improve crowd control and redistribute customers and applications
to the right places. Also, supervisors were relieved of their duty to distribute
work and were therefore able to concentrate on answering questions or reviewing
applications themselves when there was a rush. The offices were also divided into
smaller trade pods that could more easily monitor progress (Villar 1996). Different departments may be required to review
different projects depending on what is involved. These departments include the:
Planning Division, Public Works Department, Florida Department of Transportation
(FDOT), Water and Sewer Department (WASD), Dade County Health Department, Department
of Environmental Resources Management (DERM), and Fire Department. Construction
must also comply with the South Florida Building Code. 7.3.2. Types of Building Permit Processes 1. Building Permits are required for all new
construction and also for general maintenance and repairs over $500. There are no
mandatory time limits for review building permits for single-family residences take
approximately three weeks; for commercial or industrial projects approximately six
weeks. The number of building permits processed has
been fairly stable throughout the years. The average annual number is approximately
5,000 single-family units and 1,500 apartments. There was a marked increase following
Hurricane Andrew, but that has leveled off. Approximately 90 percent of these applications
are rejected their first time through the process, but most are approved the second
time through once the reviewer explains the problems with the plans. Only about
15 to 20 percent are never developed (Villar 1996). 2. Master Plan Amendments are needed to change
the land use designation before a rezoning can be sought. Amendments to the master
plan cannot be made more than twice per year, except under the following circumstances:
a) in the case of an emergency; b) if the amendment is directly related to a proposed
development of regional impact (in which case, the amendment can be considered at
the same time as the application for development approval); and c) if the amendment
is considered a small scale amendment (Chapter 163.3187,FS.). Dade County has two
amendment cycles each year, the first in May and the second in October. The second
(October) cycle in even-numbered years is an optional cycle; it is not held unless
both the county manager and the county commission concur that it is necessary The
urban development boundary is subject to amendment only once every two years, during
the first (May) cycle in odd-numbered years. The procedure for approving small scale amendments
has been changed recently Prior to this change, small scale amendments were defined
as: a residential land use of 10 acres or less with a density of 10 units per acre
or Iess, or other land use categories, singularly or in combination with residential
use, of 10 acres or less. In addition, the cumulative effect of small scale amendments
could not exceed 60 acres per year; small scale amendments could not involve the
same property more than once a year; and the proposed amendment could not involve
the same property owner's property within 200 feet of property granted a change
within the prior year. The Florida Department of Community Affair's (DCAs) role
was to conduct an "abbreviated review" of small scale amendments and issue
a notice of intent to find the amendment in compliance or not in compliance within
90 days. Small scale amendments were not subject to the statutory limits on how
often they could be submitted (Chapter 163.3187,19.94 Supplement to Florida Statutes
l993). The 1995 Legislature eliminated DCAs review
and compliance determination for small scale comprehensive plan amendments. It was
found to be ineffective to review the numerous small scale amendments submitted
each year. Compliance of small scale amendments is determined solely by local governments,
subject to challenge by affected persons. The 60-acre annual threshold was increased
to 100 acres in areas specified as urban infill, urban redevelopment, downtown revitalization,
transportation concurrency exception areas, regional activity centers, and urban
central business districts. The 10 unit per acre threshold was eliminated in existing
urban service areas outside the coastal high-hazard areas (DCA 1996). These changes reduce DCA's oversight of small
scale master plan amendments. However, in order to change the land use designation
before a rezoning can be granted, it is still necessary to go through the master
plan amendment process. 3. Zoning variances are required when a project
does not comply with the zoning code. Zoning variances must go to a public hearing
before the Zoning Appeals Board or the Board of County Commissioners, except for
administrative variances described below The Zoning Appeals Board has the authority
to consider and act upon applications on: the minimum square footage requirements
of a building; changes in zoning regulations; appeals of administrative decisions
made by administrative officials or the zoning director; special exceptions, unusual,
and new uses; use and non-use variances from regulations; and variances from subdivision
regulations (Metro-Dade County 1996, Section 33-311). The Board of County Commissioners
hears applications that involve changes to zoning and also hears appeals of Zoning
Appeals Board decisions. Zoning variances must be applied for during
the first seven days of each month. Applications are submitted to the Zoning Hearing
Section. The process takes approximately three months including: evaluation of the
case, site visits, preparation of the recommendation, advertising to the public,
and the public "hearing. Administrative zoning variances can be given
if changes are not over 50 per- cent of what is required by the code. For example,
if the code calls for a 20-foot setback, then a variance for a 10-foot setback can
be granted without a public hearing. Administrative variances do not require public
hearings. Setback variance for structures where at least 50 percent of the required
setback is provided may be approved administratively, if the applicant gets written
consent for the change from abutting property owners. Approximately 700 zoning applications are processed
per year, of these about 500 are reviewed by the Zoning Appeals Board, while about
200 go directly to the County Commission for approval. Of the 500 applications that
are heard by the Zoning Appeals Board, approximately 100 are appealed to the Board
of County Commissioners. Most of the applications that go before the Zoning Appeals
Board are setback variances (Villar 1996). 4. Site Plan Reviews are required by certain
sections of the zoning code or may be triggered by public hearings or resolutions.
According to the zoning code, site plan review is required for any multifamily development
over four units, zero lot line developments, and commercial and industrial sites.
Residential projects are submitted to the Zoning Hearing Section. Commercial and
indus-trial project reviews are performed by the Zoning Processing Section. All
site plan reviews are also referred to the Planning Division. The site plan review
process takes approximately three to four weeks. 5. Platting is required whenever land is subdivided.
A plat must be recorded prior to building permit issuance. Single-family residential
subdivisions require plats, but do not require site plan reviews. Plat review is
an administrative procedure. The subdivision/platting section does not have much
discretion in approving or denying applications. The platting requirement can be
waived for subdivisions of six or fewer units, which do not have to be recorded
in the public records. Representatives for Plat Committee Reviews include: Dade
County Public Schools, Fire Department (always present), DERM (when environmental
assessments might be required), Planning Division, Zoning and Permitting Division,
Public Works, Post Office (sometimes), Police Department (sporadically). 6. Master Model Program is used by developers
of large, residential projects. Once the different master model designs are approved
by each trade pod (e.g. plumbing, electrical, mechanical, etc.) approval for use
on a specific site takes only about four days. The department tries to restrict
the master model program to developments of over 25 units because it is time consuming
to establish initially Even when master models are used, each site must be approved
by the Zoning Division and DERM for road layout, water and sewer, and environmental
issues. Approximately 70 to 75 percent of the single-family residential units are
developed using the master model program. Of the 5,000 single-family residential
units permitted each year, about 3,500 to 3,750 go through the master model program.
The master model program has been considered for commercial projects, but because
commercial projects may have unique features, they do not lend themselves as easily
to this process (Villar 1996). 7.3.3. Complexities of the Development Permitting
Process For many reasons, the development permitting
process is a complex system. The permitting process serves a variety of public purposes.
For example, it protects people and property from inappropriate uses on neighboring
properties; it protects the public from faulty construction; and it keeps a public
record of property transactions and ownership patterns. These important functions
add up to create a complex system. It is difficult to streamline the process while
retaining these safeguards. Some of the prominent features of Metro-Dade's
development permitting process include: 1. There are no mandatory time limits for any
of the various permitting processes. 2. Permit requests are basically handled on
a first come, first served basis. 3. There is no priority given to projects based
on location. 4. All permit processors handle applications
from anywhere in the county at the Central Office. The Joint Center evaluated these features in
deciding what streamlining ÿtechniques could work for Metro-Dade County 7.3.4. County Manager Task Force Recommendations The county manager established "The County
Manager's Task Force on Construction Regulation" in September 1995. The 14-member
Task Force consisted of builders, architects, engineers, and others familiar with
the Metro- Dade County permitting process. The Zoning and Permitting Office staffed
the committee, but its personnel were not members. The recommendations of The Manager's
Task Force Final Report on Construction Regulation are already being implemented.
The primary changes concerned how the Building Code Compliance Office interacts
with the Zoning and Permitting Office. Because of the way Metro-Dade County's Code
is designed, changes in procedure will require code changes. The primary purpose of the Task Force was to
make sure that all building officials within the Building Code Compliance Office
were doing the same thing: ensuring that individual staff members dealt consistently
with the public. Because Code Compliance oversees Zoning and
Permitting's work, conflicts can arise. Zoning and Permitting staff may become more
timid (conservative) in their handling of reviews. The Task Force investigated the
interaction between Code Compliance and Zoning and Permitting and whether this oversight
role was necessary A change in this role would require an ordinance to change the
county code. Another problem is inconsistency in the field.
Different inspectors concentrate on different things. In response to this, the Task
Force recommended that the same inspector should do all inspections on the same
site. There are two offices that house construction field inspectors: the north
office (Hialeah) and the south office (SW 211 Street). The south office also has
a small processing group that handles walk-throughs on Mondays and Wednesdays. No
drop-off permitting is done at the branch offices. The Task Force also recommended
that the north and south offices should be combined to increase consistency between
the two with respect to development inspections. In the Office of Zoning and Permitting, most
of the task Force's recommendations are underway Some of the recommendations will
require code changes before they can be implemented.
7.4. Other Streamlining Methods The Joint Center also looked at other development
approval streamlining methods that have been implemented in other communities and
how they could be or are being used in Metro-Dade County The following is a brief
description of these various programs. Designate Contact Persons or Permit Expeditors
for Desirable Projects A permit expeditor "smooths the way"
for the processing of desired development projects. Assigning an expeditor or contact
person to a project can be an incentive used to attract the types of projects a
community wants. Expeditors are usually assigned to commercial or industrial projects,
but can be used for any type of development a community is trying to attract. In
some older cities they may be used to encourage redevelopment and reinvestment in
selected places. In cities deficient in affordable housing, they can reduce a developer's
carrying costs, bringing down the cost of housing. An expeditor tracks the project
through the process and can help move the application through if it stalls (Vranicar
et al. 1980). In Metro-Dade County, government projects and
major commercial projects are often assigned a contact person. Basically, the assigned
staff person would usher the project through the drop-off process. In this way,
the project would be taken out of order (placed on top of the pile) to expedite
the permitting process. The designated contact person, by ushering through projects
in the U.S. 1 corridor study area, would be giving these projects priority over
other projects. This would give developers an added incentive to build within the
study area. Pre-application Meetings Pre-application meetings can reduce the likelihood
of errors in permit applications and increase the flow of communication between
permitters and developers. Pre-application meetings increase communication while
a project is in the conceptual stage and can alert the developer to potential obstacles
before the developer has committed a lot of time and money to the project. The pre-application
meeting can give the developer an understanding of reasonable expectations for the
project (Vranicar et al.1980). In Metro-Dade County, pre-application meetings
can be requested by developers of large projects. This option is often used by out-of
state developers unfamiliar with the South Florida Building Code (Villar 1996). For the U.S. I corridor study area, the intentions
of the design guidelines in the corridor ordinances could be explained in a pre-application
meeting. It would allow the community, through the design review features of the
ordinances, an early opportunity for input into project design. By understanding
what the community wants, the project would run into fewer problems during public
hearings. Multidepartmental Review Oftentimes, applications must be routed to
several different departments for review A multidepartmental review committee can
be set up to allow joint review of a project application. In this way, each department
is aware of the comments or modifications the other department have made, and there
is less likelihood of an application bouncing back and forth between departments.
However, a joint review committee cannot substitute for technical review by specialized
staff (Vranicar et al. 1980). Metro-Dade County does include a multidepartmental
review as part of the pre-application meeting. Fire and DERM, and occasionally Public
Works, are the only external reviewers needed, and they are brought in for the pre-application
meeting when necessary (Villar 1996). One-stop Permitting Process In many communities, each individual department
has its own information counter. Each department may be located in different buildings
or in different locations within one building. In a "one-stop" permitting
process, a central counter is set up and shared by the various permitting departments. The walk-through process in Metro-Dade County
is basically a one-stop permitting process. Every part of the drop-off process is
also handled at a single location (the tenth floor of the Stephen P. Clark Center
in downtown Miami), except WASD. The department is in the process of bringing WASD
onto the same floor. Set Mandatory Deadlines Mandatory deadlines for permit application
review is an important consideration. Knowing how long the process will take reduces
the developer's sense of uncertainty However, setting mandatory review deadlines
does not always produce the intended results. If a mandatory deadline is too generous,
there is no incentive for staff to act quickly, whereas if it is too restrictive,
it may not be adhered to (Vranicar et al. 1980). Metro-Dade County does not have mandatory deadlines
for the permitting process. It has estimated target deadlines for different types
of projects and tries to maintain these time frames. Presently, a single-family
residential subdivision takes approximately 45 days, and the commercial permit processing
takes approximately 75 days. Mr. Villar stated that the commercial process is taking
too long and will be improved. He does not think setting mandatory time limits would
be necessary or desirable. The streamlining efforts implemented so far have already
improved the processing time. Further improvement is expected as more Task Force
recommendations and internal adjustments are implemented (Villar 1996). The general consensus of the Work Group was
that creating mandatory deadlines was not a desirable option. They felt that mandatory
deadlines could rush reviewers into doing a poor job or encourage them to find small
faults in order to send projects back to developers just to start the clock again
(Work Group Meeting, 10 June 1996). Fast Tracking or Designating a Project Size
Threshold Fast tracking separates out projects with minor
impacts and abbreviates the review process for them. This method is routinely used
for small subdivisions with less than a designated number of lots. The public hearing
requirement can be removed for projects under the designated threshold. In Metro-Dade County, platting requirements
can be waived for subdivisions of six or fewer units. Other than this situation,
a zoning code change would be required to designate a project size threshold (or
certain allowable land use changes) within the corridor for which a public hearing
would not be necessary This change could be written into the corridor ordinances,
but it has not been considered at this time. Zoning Code Review Zoning codes grow more complex through many
years of amendments and changes. Ideally, a zoning code should be revisited periodically
to make sure it is not outdated or contradictory However, zoning code review is
a huge and expensive undertakingÿ Metro-Dade County's zoning code has not been
reviewed. There are some inconsistencies in it. Some uses have been moved from one
zoning category to another without consideration of how that use would coexist with
other uses in the new category However, it may not be feasible for the planning
department to devote the time and energy to reviewing and rewriting a city's entire
zoning code. Planning directors may prefer to modify the code to promote certain
types of development or to allow specific projects to be undertaken, but rarely
do they have the staff or funding to revisit the entire code (Trias 1996). Reducing the number of and broadening the definitions
of zoning categories are other considerations that can be undertaken during a zoning
code review There are some theoretical questions about the need for such specific
zoning categories. The reasons for a large number of different subcategories for
residential, including single-family and multifamily commercial, and industrial
zones may be suspect. However, from a more practical point of view not only would
this proposal require a major rewriting of the zoning code, but it would be very
unpopular with a large portion of the public. Although it may have value in a small,
young community, it is not a realistic option for a largely built up, metropolitan
area the size of Metro-Dade County 7.5. Streamlining Possibilities within the
Corridor The best way to improve the development permitting
process within the South Dade U.S. 1 corridor is to designate a contact person to
expedite the permitting process for suitable projects within the study area. This
proposal will cause the least disruption to the present permitting process and will
not require code - changes to implement. It will also encourage developers to propose
and construct desirable projects within the study area, which is one of the Work
Group's primary goals. According to Mr. Villar, a contact person could
be set up for projects within the corridor. At the present time, government projects
and major commercial projects are often assigned a contact person. Basically, the
assigned staff person would "walk-through" a drop-off project. In this
way, the project would be taken out of order (placed on top of the pile) to expedite
the permitting process. A public hearing would still be needed for
every new zoning change implemented within the corridor. A zoning hearing is an
expensive ($7,000-8,000) and time-consuming (three months) process. As an incentive,
the Board of County Commissioners could instruct the department to use a "director's
application" to file rezonings within the corridor itself and save the developer
fees and some time. A director's application is submitted by the director of the
Planning, Development and Regulation Department on behalf of the developer, and
therefore the fee can be waived. It is also possible for the permitting section
to notify the Joint Center when a permit is applied for within the study area, for
the duration of Phase III (until December 1997). This would allow the Joint Center
and the South Dade Planning and Design Work Group to work with the applicant early
enough in the design process to effect desired changes before too much time or money
had been invested in the project (Villar 1996). After the conclusion of Phase III,
a new organization, such as an ongoing South Dade Planning and Design Work Group,
local community councils, or neighborhood associations, could be chosen to fulfill
this role. 7.6. Conclusion A primary method for streamlining the development
approval process within the study area will derive from the corridor ordinances.
These ordinances will give direction for the type of development that will meet
with easier approval. " Also, having a single contact person, who is familiar
with the corridor and with the corridor ordinances, assigned to all projects within
the study area could be an important feature in attracting developers to work in
the study area. Besides these two approaches, the county has already completed a
streamlining study Some of the recommendations of this study are in use. Others
may be implemented soon.
|